- 11 roomsFlooring scope
- 6 daysTime on site
- Room by roomDelivery sequence
- Fixed priceConfirmed before work
The Requirement
A commercial accommodation operator required flooring replacement across guest rooms while the property remained operational. The work needed a confirmed price, controlled sequencing, and a clear handover record for each completed area.
Scope Completed
Existing carpet and vinyl tile were stripped and disposed of across 11 rooms. Substrates were prepared before vinyl plank flooring was supplied and installed through the guest rooms, corridors, and kitchenette areas included in the scope.
Delivery and Outcome
The rooms were completed in sequence rather than opened simultaneously. The full scope was delivered over six days, allowing the accommodation property to continue operating while completed rooms were handed back with photographic close-out.
Recorded Condition and Completed Work



Clear Answers About This Work
What flooring work was completed at the Parkes motel?
Existing carpet and vinyl tile were removed across 11 rooms, the substrates were prepared, and vinyl plank flooring was supplied and installed through the areas included in the scope.
How long did the motel flooring refurbishment take?
The confirmed 11-room scope was completed over six days on site.
How was disruption to the operating motel managed?
Work was sequenced room by room so completed areas could be handed back progressively while the property continued operating.